Mini-feasibility study by Sustrans
In January 2019, a mini-feasibility study of the old railway line and the proposed route was carried out by Sustrans, the UK walking and cycling charity, accessing the parts that are open to the public (much of the route is under private ownership). It found that if use could be obtained, it would make an excellent foundation for a walking and cycling path.
The main contraints to construction of the route were found to be private landownership, ecological issues (such as the significant bat roost at Talylln tunnel), and areas where the line has been built over or replaced by highway.
The survey gave a rough estimated construction cost of £6,250,000, excluding costs of design, project management and contingency. It also highlighed the importance of future maintenance of the route, and to that end, suggested a sealed tarmac path at a width of 2.5m.
It suggested developing a phased approach to route development and construction that can stand alone.